Nebius Q3 Revenue Hits $980.8M as Guidance Tightens

Nebius posted official Q3 2026 results on November 12: $980.8 million of revenue, 2026 guidance now at the low end of $3.0–$3.4 billion, and an initial 2027 outlook. This is a post-results account, not a preview rewrite.

Nebius Group N.V. on November 12, 2026, published its unaudited financial results for the three and nine months ended September 30, 2026, together with founder and chief executive officer Arkady Volozh’s quarterly letter to shareholders. The official materials are posted on the company’s newsroom results page, with the full press release and shareholder letter available as PDFs from that page and from the investor hub. Management held an earnings webcast at 8:00 a.m. Eastern Time the same day, before the regular U.S. cash-equity open. This article is a post-results account of those official documents. It is not a rewrite of the earlier Nebius Q3 preview, and it does not treat Applied Materials’ fiscal fourth-quarter report or Cisco’s fiscal first-quarter report, both still scheduled for after Thursday’s close, as already released.

The headline print is a large step-up in scale accompanied by a tighter near-term revenue message and a much larger capital-expenditure plan. Consolidated revenue was $980.8 million in the third quarter, up 571 percent from $146.1 million a year earlier. For the nine months, revenue was $1,962.1 million, up 549 percent from $302.1 million. Adjusted EBITDA, a non-GAAP measure defined in the release, was $465.8 million, compared with an adjusted EBITDA loss of $5.2 million a year earlier. Net loss from continuing operations narrowed to $37.5 million from $119.6 million. Adjusted net income was $90.9 million, compared with an adjusted net loss of $100.4 million. Those are official line items. The more consequential news for anyone following AI-infrastructure funding sits in the letter’s updated 2026 guidance and the company’s first formal 2027 outlook.

Key takeaways from the official documents

  • Third-quarter revenue was $980.8 million, and nine-month revenue was $1,962.1 million, both official figures in the November 12 press release.
  • The company now expects 2026 revenue at the low end of its previously stated $3.0 billion to $3.4 billion range, after some third-party capacity slipped into the first half of 2027. The contracts behind that capacity, the letter says, remain in place.
  • 2026 capital expenditures are now expected at approximately $27 billion, above the prior $20 billion to $25 billion range, as the company invests in capacity for 2027, particularly at owned sites.
  • Annual recurring revenue, previously guided to $7 billion to $9 billion by December, is now expected to exceed $7 billion for the month of February, a shift of about two months, “even before New Jersey ramps up to full capacity.”
  • The initial 2027 outlook is $12 billion to $13 billion of revenue, pre-tax breakeven in the fourth quarter of 2027 after financing costs, and $40 billion to $45 billion of capital expenditures, sized for more than 1 gigawatt of new capacity.
  • Prepayments on third-quarter agreements of one year or longer covered more than 100 percent of associated capex, up from 50 to 60 percent in the second quarter. Annual contract value per megawatt exceeded $25 million in the third quarter, and GPU-hour prices rose on average by more than 20 percent versus the second quarter.
  • These results should be read next to CoreWeave’s already released official third-quarter figures, not as a substitute for Thursday’s still-unreleased semiconductor and networking reports.

The official third-quarter scorecard

The press release presents consolidated results that include Nebius AI cloud, the core business, plus Avride and TripleTen. After a third-party investment in the second quarter of 2025, Nebius no longer consolidates Toloka and reports that stake as an equity-method investment; prior Toloka results were reclassified to discontinued operations. Readers comparing year-over-year rates should stay on the continuing-operations lines the company itself highlights.

Consolidated item (USD millions)Q3 2025Q3 2026Change9M 20259M 2026Change
Revenues146.1980.8571%302.11,962.1549%
Adjusted EBITDA / (loss)(5.2)465.8n/m(79.9)831.5n/m
Net income / (loss) from continuing operations(119.6)(37.5)-69%278.6393.341%
Adjusted net income / (loss)(100.4)90.9n/m(273.7)(42.6)-84%

The operating-cost table is just as important as the headline revenue line, because it shows the mix of cash costs, development spending, and depreciation that a rapidly scaling compute platform generates. Cost of revenues was $219.7 million, or 22 percent of revenue, down from 29 percent a year earlier. Product development was $118.6 million, or 12 percent of revenue, down from 31 percent. Sales, general and administrative expense was $237.4 million, or 24 percent of revenue, down from 61 percent. Depreciation and amortization was $354.7 million, or 36 percent of revenue, down from 68 percent. Total operating costs and expenses were $930.4 million, or 95 percent of revenue, compared with 189 percent a year earlier. Share-based compensation expense was $58.7 million, up from $26.1 million. These ratios are official percentages from the release; they are not a complete margin analysis on a GAAP operating-income basis, and they should not be rewritten as if adjusted EBITDA were a cash figure.

Operating item (USD millions)Q3 2025Q3 2026ChangeQ3 2026 % of revenue
Cost of revenues42.9219.7412%22%
Product development44.9118.6164%12%
Sales, general and administrative89.5237.4165%24%
Depreciation and amortization99.0354.7258%36%
Total operating costs and expenses276.3930.4237%95%
Share-based compensation expense26.158.7125%—

Nine-month continuing-operations net income of $393.3 million is higher than the third-quarter loss would suggest, and the cash-flow statement in the release includes a large gain from revaluation of investments in earlier periods. That is a reminder, already familiar to readers of the company’s prior letters, that reported net income can move for reasons other than the run-rate cloud business. This article does not collapse those items into a single “earnings beat” slogan. The press release is explicit that adjusted EBITDA and adjusted net income are non-GAAP measures, and it provides definitions and reconciliations rather than inviting readers to treat them as substitutes for U.S. GAAP.

The 2026 guidance change, in the letter’s own words

The shareholder letter is where the company updates its 2026 guide. The wording is specific and should be quoted as a guide change, not as a completed year. “We are updating our 2026 guidance for one change: some third-party capacity we expected to come online this year is now scheduled for the first half of 2027. The contracts behind that capacity remain in place.” Revenue is now expected “at the low end of our $3.0-3.4 billion range.” The adjusted EBITDA margin guide is “unchanged, at approximately 40 percent.” Capital expenditures are “approximately $27 billion, above our $20-25 billion range, as we invest in capacity for 2027, in particular at our owned sites.”

The ARR revision is easy to misread if it is treated as a cancelled contract. It is a timing shift. The company “had guided to $7-9 billion by December” and “now expect[s] ARR to exceed $7 billion for the month of February, a shift of about two months, even before New Jersey ramps up to full capacity.” The letter separately discusses New Jersey third-party delays and a transition of the power source to Bloom Energy fuel cells, with initial generation installed and capacity now being scaled. Contracted power guidance is unchanged: “We continue to expect 5 GW of contracted power by year-end, from more than 4 GW today.”

Two cautions follow directly from those sentences. First, ARR annualizes a single month. The 2027 outlook section later says the company will, from 2027, “provide guidance for revenue, pre-tax earnings and capacity,” because “ARR annualizes a single month, and does not reflect the scale of our business.” Using the February ARR remark as a 2026 revenue forecast would be a category error. Second, the revenue guide is now pinned to the low end of a range that was already public. A reader who only sees “$980.8 million, up 571 percent” and skips the letter will miss the capacity-timing issue that management itself flags.

The first official 2027 outlook

The letter’s 2027 section is labeled “initial outlook,” and it is forward-looking. Revenue is put at “$12-13 billion, approximately four times our 2026 revenue.” Pre-tax profit is guided to “breakeven in Q4 2027,” “calculated after financing costs, and assum[ing] a five-year depreciation life for compute.” Capital expenditures are “$40-$45 billion, sized for more than 1 GW of new capacity.” The company “expect[s] to cover 75-85 percent of our capex through advanced prepayments and asset-backed financing [from] investment-grade customers along with our balance sheet.” Power guidance is that the firm “continue[s] to expect to bring online more than 1 GW of new capacity each year.”

Those figures are large enough to dominate the investment debate around the stock, and they are also incomplete in ways the letter itself marks. They are an outlook, not a completed year. The pre-tax breakeven target depends on a stated depreciation assumption and on financing costs that will themselves depend on how much of the $40 billion to $45 billion is funded by prepayments, asset-backed facilities, convertible or other corporate debt, and equity. The 75 to 85 percent coverage claim is an expectation about 2027 funding mix, not a third-quarter cash-flow fact. This article does not convert the outlook into a price target or a guaranteed build schedule.

Prepayments, contract value and pricing

The commercial metrics in the letter explain why management is willing to raise 2026 and 2027 capex even while sliding 2026 revenue to the low end. Prepayments on third-quarter agreements covered more than 100 percent of associated capex, “including data center construction and networking, up from 50-60 percent in Q2.” A footnote defines that coverage as being calculated from deals of one year or longer, including GPU, data-center construction and leasehold improvement costs. “More than 90 percent of contract value signed in the third quarter carried a prepayment, and the weighted average prepayment as a share of contract value rose by approximately 20 percentage points quarter-on-quarter.” The letter says this trend is continuing into the fourth quarter.

Payback on a revenue basis, excluding the benefit of prepayments, improved to 1 year and 7 months in the third quarter from 1 year and 10 months in the second quarter for comparable one-to-three-year deals, “driven primarily by higher contracted pricing on new deals.” Annual contract value per megawatt “exceeded $25 million” in the third quarter, “up from >$20 million on our Q2 deals,” on a weighted average of deals up to five years. “Prices in Q3 rose on average more than 20 percent per GPU-hour versus Q2.” The company also describes new pricing mechanisms: reserve auctions that “cleared more than 15 percent above our reserve price,” live spot prices that “at times exceed[ed] our on-demand rate,” and short-term clusters “pricing at more than twice the reserved rate.”

A chart page in the letter states that $12 billion of total contract value has been signed since the beginning of the third quarter, and that enterprise AI platforms joined frontier labs and AI-native companies. Those are company figures from the official letter, not third-party estimates. They still leave customer-level revenue concentration undisclosed in the public tables. This article does not invent a customer list or a percentage of revenue from any named counterparty, even though the letter discusses long-term agreements with Microsoft and Meta in the financing section as contracts that “can be financed the same way” as a July asset-backed facility.

The funding stack behind a larger capex plan

The letter’s capital-requirements section is unusually detailed and should be read as a menu, not as a single committed raise. Prepayments and asset-backed financing of existing investment-grade contracts “alone are expected to fund 75%–85% of our $40–45 billion of capex in 2027.” The company expects “$10 billion in committed customer prepayments in 2026, rising to $17–20 billion in 2027,” received “well in advance.” The 2027 range “is not a ceiling” and “depends on how we allocate capacity across contract types.” In July the company “closed the first facility under our asset-backed financing framework: $775 million at SOFR plus 2.50%, secured against long-term agreements with an investment-grade customer.” It points to “more than $40 billion of similar committed revenue” as the basis for treating that structure as repeatable.

The balance-sheet side of the same discussion is also official. Cash and cash equivalents were $7.4 billion at quarter-end. This year, the letter says, external capital has included “$5.75 billion of convertible notes in August, approximately $1.0 billion of net proceeds under our at-the-market program in the third quarter — a flexible tool, not a commitment — and short-term facilities on attractive terms, such as the $3.5 billion senior secured facility with Citi in October.” The ATM is expressly described as optional, not as a promise to issue a set amount of equity. Readers should not treat any of those figures as incremental new raises announced for the first time on November 12 unless the letter presents them that way; several were earlier transactions now being restated as part of the funding mix.

The company’s preferred construction model is also stated plainly. “We prefer to build our own sites, which give us greater control over execution and better economics.” Owned sites “are on time or ahead of schedule” and are expected to “make up most of the gigawatts we bring to market in the future.” “Where we rely on third parties, there have been delays,” including in New Jersey. That sentence is the operational counterpart of the 2026 revenue-guide change. A build that slips into 2027 can coexist with rising 2026 capex if the firm is spending now on owned capacity for next year. It is a coherent official story. It is not proof that every campus will arrive on the new date.

How this print sits next to CoreWeave — and what is still unreleased

CoreWeave, a larger listed neocloud, already reported official third-quarter results on November 10, including $3.66 billion of revenue and a raised 2026 outlook, as set out in the company’s official earnings release and in our post-results account of that print. The two companies are not interchangeable. They have different revenue bases, capital structures, customer mixes and accounting presentations. The useful comparison is qualitative and limited: both are asking investors to fund a multi-year GPU and data-center build, both emphasize contracted demand and prepayments or backlog, and both are now reporting into a market that has spent several weeks debating whether AI infrastructure capital expenditure is ahead of monetization. Nebius’s letter even opens the recent industry debate directly: “In recent weeks our industry has been asked questions about how the AI build-out will be financed.” Volozh’s answer is the prepayment and balance-sheet discussion summarized above, not a denial that the question exists.

What this package will not do is preview, again, the reports that have not been issued. Applied Materials’ fiscal fourth quarter and Cisco’s fiscal first quarter are still scheduled for after the Thursday close, with calls at 4:30 p.m. Eastern, as already outlined in the Thursday AI-infrastructure earnings setup. Nvidia’s fiscal third-quarter report remains scheduled for November 17. October producer prices remain scheduled for 8:30 a.m. Eastern on Friday, November 13. None of those events is treated here as a known result. This account does not invent a regular-session share-price close for the session after the Nebius release.

What the official documents do not settle

Several items remain outside the public tables. The release does not, in the summary financial highlights, isolate Nebius AI cloud revenue from Avride and TripleTen, so the $980.8 million figure is a consolidated number. Customer-level concentrations are not broken out. The 2026 low-end revenue guide does not quantify the dollar amount of revenue deferred by the third-party capacity delay. The $12 billion to $13 billion 2027 revenue outlook is a range, and “approximately four times our 2026 revenue” will depend on where 2026 actually lands inside the $3.0 billion to $3.4 billion band. The 75 to 85 percent capex-coverage expectation is not a committed financing. Cash-flow classification, working-capital swings, and the precise path from a third-quarter continuing-operations loss to a 2027 pre-tax breakeven target require the reconciliations and later filings, not a slogan.

Secondary coverage, including a CNBC report on the morning of November 12, discussed share-price weakness and compared the print with analyst estimates. Those comparisons can be useful color, but consensus figures are not official company numbers, and premarket or intraday moves are not closing prices. This article keeps official financials on the company’s own documents and treats any market-color commentary as dated and secondary.

Frequently asked questions

Did Nebius already report third-quarter 2026 results?

Yes. The official newsroom release and shareholder letter are dated November 12, 2026, and cover the three and nine months ended September 30, 2026. The webcast was scheduled for 8:00 a.m. Eastern Time the same day.

What are the official headline financials?

Revenue was $980.8 million in the third quarter and $1,962.1 million in the first nine months. Adjusted EBITDA was $465.8 million in the third quarter. Net loss from continuing operations was $37.5 million. Adjusted net income was $90.9 million. All of those figures come from the official press release.

What changed in the 2026 outlook?

The letter now expects revenue at the low end of the $3.0 billion to $3.4 billion range, keeps an approximately 40 percent adjusted EBITDA margin, lifts capex to about $27 billion from a prior $20 billion to $25 billion range, and moves the ARR checkpoint of more than $7 billion from December to February. Contracted-power guidance of 5 gigawatts by year-end is unchanged.

What is the official 2027 outlook?

It is an initial outlook: $12 billion to $13 billion of revenue, pre-tax breakeven in the fourth quarter of 2027 after financing costs with a five-year compute depreciation assumption, and $40 billion to $45 billion of capital expenditures. It is not a reported year.

Does this article include Applied Materials or Cisco results?

No. Those reports had not been issued as official results. They should not be inferred from the Nebius print.

Sources and research limits

Primary sources are the official November 12, 2026, Nebius newsroom release, the official “Nebius Q3 2026 Financial Results Press Release” PDF, the official shareholder letter PDF dated November 12, 2026, and the investor-hub materials page. CoreWeave comparisons use that company’s official November 10 release. Official results for the November 12 30-year Treasury auction, and official Applied Materials and Cisco prints scheduled after the Thursday close, are not treated here as published facts. Forward-looking statements in the letter are identified as such and are not treated as historical facts.

Disclaimer: This content was generated with the assistance of artificial intelligence (AI) and has been reviewed by our editorial team. It is intended for informational purposes only and should not be construed as financial, investment, or legal advice. Cryptocurrency investments involve significant risk.